The schedule

Order the work on each machine and see what is late or over capacity.

Updated 23 September 2026

Why
A lead time is only honest when it comes from what each machine can actually do.
What
The schedule is a day or a week board with a lane per machine and each open job as a block sized by setup plus standard minutes.
How
Put the jobs in the order you want; the board works out where each one ends against the machine's available minutes.

Reorder the work

  1. Step 1.

    Open /app/machinist/schedule and pick Day or Week.

  2. Step 2.

    Drag a block within its lane, or use Move up the queue and Move down the queue.

  3. Step 3.

    To change machine, drag the block onto another lane or use Move to a machine.

Jobs with no machine sit in the No machine column. They are listed, not planned, until you move them onto one.

What the board tells you

MarkerMeans
LatePlanned to finish after the job is due
Over capacityMore planned minutes than the machine's available minutes
Not knownThe machine module gave no estimate, so the block adds nothing to the load
ends 1h 55m into the day, for exampleHow far into the working day the job ends. Not a clock time: nothing records when your day starts

A machine with no Available minutes a day plans nothing; set it on Machines.

The board is the order you set. Nothing reorders it on its own: there is no solver and no AI, and the same jobs always give the same board. Moving a job onto a machine its operator is not certified for is refused.